Angi
Homeowner-to-pro quotes for electrical work, including panel upgrades, EV chargers, and generator hookups.
Referral pendingDirectory / FL / Unincorporated Orange County
EV charger / NEMA 14-50
In unincorporated Orange County, a new electrical outlet or a moved outlet requires an electrical permit. Installing a new NEMA 14-50 receptacle or a new dedicated EV-charging circuit is new wiring, not a like-for-like plug-in appliance swap — the county’s “Do I need a permit?” guide says an appliance that merely plugs into an existing outlet does not need a permit, but a new or relocated outlet does. Apply online through Fast Track. Homeowners doing their own work may use the owner-builder exemption in Florida Statute 489.103(7)(a) and must complete the Owner-Builder Disclosure Statement and identity verification. The Orange County Fee Directory for Fiscal Year 2026–2027, effective October 1, 2026, lists a $38 minimum electrical permit and, for additions or alterations that do not change the service, a $39 fee for valuation up to $1,000 plus $11 for each additional $1,000, or $39 for a simple installation of one item of equipment. The county calculates the exact fee at application. The City of Orlando is a different AHJ.
Orange County’s official “Do I need a permit?” guide, which is for reference and is not exhaustive, answers “A new electrical outlet or move an outlet?” with “Yes, you need an electrical permit.” The same guide says an appliance that plugs into an existing outlet does not require a permit. A hardwired EV charger, or a new NEMA 14-50 receptacle on a new 240-volt circuit, is a new outlet and new circuit, so it falls on the permit-required side of that distinction. The Electrical Permits page also says that if the electrical work is part of new construction or an addition, a building permit is required, and that if no meter service is being installed, a valuation of materials and fixtures is required. For any required permit, the guide says at least a final inspection must be passed. Email EResQuestions@ocfl.net if your scope is unusual.
The county’s Electrical Permits page says homeowners doing their own work must complete an Owner-Builder Disclosure Statement and follow the Owner-Builder Online Permitting instructions. An owner-builder may act as contractor under the exemption in Florida Statute 489.103(7)(a). The “Do I need a permit?” page adds that if the permit is obtained by a homeowner and not a contractor, staff will request the Owner-Builder Disclosure Form if it was not already submitted, plus completed owner video verification. Official instructions tell owner-builders to register a non-license-holder Fast Track account, apply online, and email OwnerVerification@ocfl.net to schedule identity verification, bringing government photo ID. Only a licensed contractor may give power of attorney to an agent, and that power of attorney must be original, site-specific, and notarized. If the value of work exceeds $5,000, a Notice of Commencement is required.
New permit applications and inspection requests must be submitted online through Fast Track. The county’s Permits & Licenses page says no new permit applications or plans are accepted in person; in-person appointments are for information only and must be scheduled in Fast Track. Confirm that the property is in unincorporated Orange County, not the City of Orlando or another municipality.
The Orange County Fee Directory for Fiscal Year 2026–2027, effective October 1, 2026, is a reference compilation of county fees, not itself a separately enacted ordinance. It warns users to treat it as a reference and not as a legally binding document. For a typical EV-charger or NEMA 14-50 circuit that does not change the electric service, the most relevant published line items are the alteration fees that apply when service is not changed, and the “simple installation of one item of equipment” fee. If the project also upgrades the service or panel, different amperage-based fees apply. The county calculates the exact fee in Fast Track.
| Item | Amount | Source note |
|---|---|---|
| Minimum electrical permit fee | $38.00 | Fee Directory, Electrical Permit Fees, introductory minimum. |
| Additions, alterations, and repairs not requiring a change in service, up to and including $1,000 valuation | $39.00 | Paragraph (C). Valuation is based on material and labor costs. This is the most likely starting point for a new circuit that does not upgrade the service, but the county — not this page — decides which paragraph applies. |
| Each additional $1,000 valuation or fraction thereof (no service change) | $11.00 | Paragraph (C). |
| Simple installation of one item of equipment, regardless of amperage | $39.00 | Paragraph (D). Ask the county whether a single EV charger or a single 14-50 receptacle is scored under (C), (D), or another row. |
| If the service is upgraded: 1-phase 240-volt, 0 to 150 amperes | $77.00 | Paragraph (1). Higher amp and three-phase rows are also in the directory. Paragraph (B) says that when a change in service is required, the fee is the applicable permit fee for the difference between the new and previous service amperage, if positive. |
Do not assume a $38 or $39 total until Fast Track shows it. If the job includes a panel upgrade, a new meter, or valuation over $1,000, the fee will be higher. The Fee Directory’s effective date is October 1, 2026 (FY 2026–2027).
Orange County Fee Directory, Fiscal Year 2026–2027 (effective October 1, 2026)
Yes, if you are adding a new outlet or a new circuit. Orange County’s “Do I need a permit?” guide says a new or moved electrical outlet requires an electrical permit. An appliance that only plugs into an existing outlet does not. A new 14-50 or a hardwired charger is a new outlet and circuit.
Yes, if you qualify as an owner-builder under Florida Statute 489.103(7)(a). Complete the Owner-Builder Disclosure Statement, follow the county’s owner-builder Fast Track instructions, and finish identity verification. If you hire a licensed contractor, that contractor should pull the permit.
The FY 2026–2027 Fee Directory, effective October 1, 2026, lists a $38 minimum electrical permit. For work that does not change the service, it lists $39 for valuation up to $1,000 plus $11 per additional $1,000, and $39 for a simple installation of one item of equipment. The county chooses the correct row and shows the total in Fast Track. A service or panel upgrade uses different amperage-based fees.
No. The City of Orlando has its own permitting office. This page is only for unincorporated Orange County, which uses Fast Track and the Division of Building Safety at 201 South Rosalind Avenue.
Every factual claim on this page is drawn from the government pages below, last checked on the date shown. If a link has moved, start at the AHJ website.
Most electrical permits still end with a licensed electrician doing the work — or at least signing off on an inspection. When referral programs are activated, the buttons below will go to those partners. Until then, hire a licensed electrician who is registered with the local AHJ, and verify their license with the state licensing board.
Homeowner-to-pro quotes for electrical work, including panel upgrades, EV chargers, and generator hookups.
Referral pendingPay-per-lead contractor matching for home-improvement trades. Modernize also sells generator leads to contractors (install, hookup, transfer switch).
Referral pendingA reserved slot for a direct referral agreement with a licensed electrical contractor who already works in this jurisdiction.
Ready to activate