Quick answer

Inside the City of Houston, a residential standby generator needs both a single-trade electrical permit and a single-trade plumbing permit. Each licensed contractor pulls and is responsible for their own permit and inspections. Electrical permits are issued only to master electricians registered with the city, and the Electrical Inspections page states that all electrical work must be performed by a licensed electrical contractor. The 2026 Building Code Enforcement Permit Fee Schedule sets a $91.06 minimum electrical permit fee and a $33.56 non-refundable administrative fee; generator-size charges are listed by kilowatt and are still subject to those minimum and administrative fees. Houston also publishes a Residential Standby Generator Permit & Inspection Guide (CE-1060) with clearance and inspection checkpoints. A generator permit does not waive the city’s Chapter 30 noise ordinance.

Yes — electrical and plumbing permits

Do I need a permit?

The official Generator Permit page (HPWCODE1118) says registered electrical contractors who wish to install a standby generator must apply for an electrical permit. The CE-1060 Residential Standby Generator Permit & Inspection Guide is more specific: single-trade electrical and plumbing permits are required, and each licensed contractor must pull and be responsible for their own permits and inspections. The plumbing permit covers the gas or fuel piping from the meter to the generator. Plan review and inspection are both listed as required on the generator permit page. The permit is valid for 180 days and is not listed as renewable on that page.

No — licensed contractors only

Can a homeowner pull it?

Houston’s Generator Permit page states that electrical permits are only issued to registered master electricians, and that licensed electrical contractors must register their master and contractor licenses with the city before applying in iPermits. The Electrical Inspections page states that all electrical work must be performed by a licensed electrical contractor, and that the licensed electrical contractor performing the work schedules the inspections. CE-1060 likewise requires each licensed contractor to pull the electrical or plumbing permit. A Houston homeowner should hire a licensed electrical contractor (and a licensed plumber for the gas piping) rather than trying to pull these permits themselves.

Official AHJ office

Office
City of Houston Public Works — Building Code Enforcement, Electrical Inspections
Division
Electrical Inspections (plumbing inspections are a separate section)
Address
1002 Washington Ave., 4th Floor, Houston, TX 77002
Phone
832-394-8860
Email
hpcelectricalsection@houstontx.gov
Hours
8:00 a.m. to 4:30 p.m. (hours published on the Generator Permit and Electrical Inspections pages). To find the inspector assigned on the day of inspection, the generator page says to call 832-394-8860 between 7:15 a.m. and 8:00 a.m.
Portal
iPermits

This office covers properties inside the City of Houston. Unincorporated Harris County uses a different permitting authority.

More official contacts

Fees

Use the 2026 Building Code Enforcement Permit Fee Schedule, which states that all permit fees are subject to the minimum and administrative fees. The electrical minimum is $91.06 and the non-refundable administrative fee is $33.56, so an electrical permit totals at least $124.62 before any additional listed items. The official Generator Permit landing page still displayed older kilowatt line items and a “$3.96 to $11.95” fee range when this page was researched; those older figures should not be used if they conflict with the 2026 schedule. Confirm the live total in iPermits.

ItemAmountSource note
Minimum electrical permit fee (2026 schedule) $91.06 Applies to electrical permits. Listed both in the general administrative section and under Electrical Permit Fees.
Administrative fee, non-refundable (2026 schedule) $33.56 Charged for issuing each permit or receipt, per the 2026 schedule and the CE-1057 application form (revised September 2026).
Heaters/generators up to and including 1 kW $4.02 2026 schedule and CE-1057. Subject to the $91.06 minimum and $33.56 administrative fee.
Heaters/generators over 1 kW through 10 kW $11.41 2026 schedule and CE-1057. Subject to the minimum and administrative fees.
Heaters/generators over 10 kW $8.05 plus $1.81 for each additional kW over 10 kW 2026 schedule and CE-1057. A typical whole-house unit is over 10 kW; the calculated kW charge may still be below the $91.06 minimum, in which case the minimum applies. Additional listed items (outlets, panels, and so on) can increase the fee.
Reinspection fee $94.00 2026 schedule and CE-1057. The generator permit page also warns that repeatedly failed inspections may be charged a reinspection fee plus an admin fee.
Plumbing permit for gas piping Separate fee, not in the electrical table CE-1060 requires a plumbing permit. Get that amount from the 2026 fee schedule’s plumbing section or from the plumbing contractor’s iPermits application.

The Generator Permit page (HPWCODE1118) listed older kW prices ($3.75 / $10.65 / $7.51 / $1.69) and a separate “Fee: $3.96 to $11.95” line, plus the same $33.56 administrative fee, when this page was verified on November 27, 2026. The 2026 fee schedule PDF and the September 2026 CE-1057 form are the clearer current sources. Always confirm in iPermits before paying.

2026 Building Code Enforcement Permit Fee Schedule

How to apply

  1. Confirm the property is inside the City of Houston, not unincorporated Harris County or another city.
  2. Hire a licensed electrical contractor and, for natural-gas or propane piping, a licensed plumber. The electrician’s master and contractor licenses must be registered with the City of Houston Electrical Inspections section (hpcelectricalsection@houstontx.gov; see form CE-1203).
  3. The electrical contractor applies in iPermits at the official address published on the Generator Permit page, completes the electrical permit application (CE-1057 is the form used when a paper or email application is required), and pays the fees. First-time iPermits users need the iPermits Acknowledgement Form. After fees are paid, print the permit.
  4. The plumber separately pulls the plumbing permit for the fuel piping. Large or unusual projects may also need plan review; the generator permit page lists plan review as required and says large-scale commercial projects may need plan review before approval.
  5. Keep the manufacturer’s installation manual and the permits on the jobsite for the entire inspection process, as CE-1060 requires.

Inspections

  1. The licensed electrical contractor schedules electrical inspections online or through the IVR system at 713-222-9922, using a 4-digit scheduling PIN. Both the electrical master and contractor registrations must be in good standing. Keep a copy of the permit (and approved plans, if any) on site.
  2. CE-1060 electrical checkpoints include: a pad inspection before pouring concrete when the pad is poured in place (location only); site inspection of clearances from the generator or its housing to lot lines (2 feet minimum), combustible exterior building walls including wood-framed brick veneer (5 feet minimum), and openings in an exterior wall (5 feet minimum, citing NFPA 37 Sec. 4.1.4); location relative to the existing electrical panel; wiring and conduit; and the electrical contractor’s load analysis showing that the generator and transfer switch are sized for the designated loads.
  3. CE-1060 plumbing final checkpoints include the gas piping from the meter to the generator, the listed flex connector, any required regulator, meter and piping size, and equipment location and orientation relative to the gas meter and other equipment that needs maintenance access, again citing NFPA 37 Sec. 4.1.4.
  4. Inspection requirements follow the manufacturer’s installation manual, Houston Construction Codes, and NFPA standards, whichever is more restrictive.

Common pitfalls

Questions people actually ask

Can I install a whole-house generator in Houston myself to save money?

Not under the city’s published electrical-permit rules. Electrical permits are issued only to registered master electricians, and all electrical work must be performed by a licensed electrical contractor. A licensed plumber must also pull the plumbing permit for the fuel piping.

Do I need both electrical and plumbing permits?

Yes. CE-1060, the city’s Residential Standby Generator Permit & Inspection Guide, says single-trade electrical and plumbing permits are required, and each licensed contractor is responsible for their own permit and inspections.

How much is the Houston generator electrical permit?

The 2026 fee schedule lists generator charges by kilowatt, but every electrical permit is also subject to a $91.06 minimum fee and a $33.56 non-refundable administrative fee (a floor of $124.62). Additional listed items can raise the total, and the plumbing permit is separate. Confirm the live amount in iPermits. Do not use the older kW prices still shown on the Generator Permit landing page if they disagree with the 2026 schedule.

What clearances does Houston check?

CE-1060 lists minimum distances from the generator or generator housing of 2 feet to lot or property lines, 5 feet to combustible exterior building walls (including wood-framed brick veneer), and 5 feet to openings in an exterior wall, citing NFPA 37 Sec. 4.1.4. Inspectors also use the manufacturer’s manual and Houston codes and apply whichever requirement is more restrictive.

Official sources

Every factual claim on this page is drawn from the government pages below, last checked on the date shown. If a link has moved, start at the AHJ website.

  1. City of Houston — Generator Permit (HPWCODE1118) — accessed November 27, 2026; https://www.houstonpermittingcenter.org/hpwcode1118
  2. 2026 Building Code Enforcement Permit Fee Schedule — accessed November 27, 2026; https://www.houstonpermittingcenter.org/media/2636/download
  3. CE-1060 Residential Standby Generator Permit & Inspection Guide (revised September 2024) — accessed November 27, 2026; https://www.houstonpermittingcenter.org/media/1886/download
  4. CE-1057 Electrical Building Permit Application (revised September 2026) — accessed November 27, 2026; https://www.houstonpermittingcenter.org/media/991/download
  5. City of Houston — Electrical Inspections — accessed November 27, 2026; https://www.houstonpermittingcenter.org/building-code-enforcement/electrical-inspections
  6. iPermits (URL published on the Generator Permit page) — accessed November 27, 2026; https://www.pdinet.pd.houstontx.gov/ILMS_Online_Permits/default.asp
  7. 2026 Fee Increase Notice — accessed November 27, 2026; https://www.houstonpermittingcenter.org/news-events/2026-fee-increase-notice

Need a licensed electrician?

Most electrical permits still end with a licensed electrician doing the work — or at least signing off on an inspection. When referral programs are activated, the buttons below will go to those partners. Until then, hire a licensed electrician who is registered with the local AHJ, and verify their license with the state licensing board.

Angi

Homeowner-to-pro quotes for electrical work, including panel upgrades, EV chargers, and generator hookups.

Referral pending

Modernize

Pay-per-lead contractor matching for home-improvement trades. Modernize also sells generator leads to contractors (install, hookup, transfer switch).

Referral pending

Local licensed contractor

A reserved slot for a direct referral agreement with a licensed electrical contractor who already works in this jurisdiction.

Ready to activate