Directory / GA / Decatur

Electrical permits and homeowner DIY rules

Electrical permits in Decatur, GA: trade permits, fees, and homeowner rules

City of Decatur, Georgia (not unincorporated DeKalb County) · Official sources verified November 27, 2026 (America/Chicago)

Quick answer

Inside the City of Decatur, a separate electrical trade permit is required when you install, enlarge, alter, repair, remove, convert, or replace an electrical system, regardless of project value. Applications are accepted only through Community Core — the city no longer takes paper, email, or in-office permit applications. The adopted FY 2025–26 fee schedule (approved June 16, 2025) lists a $90 minimum electrical permit, plus itemized device and service charges, and a $25 e-permitting and digital plan review fee per item. Homeowners who want to act as their own contractor must file the city’s Homeowner Permit Letter of Indemnification Affidavit. This page is for the City of Decatur only; unincorporated DeKalb County is a different AHJ.

Yes, for electrical-system work of any value

Do I need a permit?

The city’s How to Obtain a Permit page states that requirements come from Unified Development Ordinance §10.1.1, and that separate trade permits are required when installing, enlarging, altering, repairing, removing, converting, or replacing any electrical system, regardless of value. Building permits are also required for constructing, enlarging, altering, repairing, moving, demolishing, or changing the occupancy of a structure, for repairs and maintenance valued at $1,000 or more, and for roofing or structural work. If you are only sure that electrical work is involved, plan on an electrical trade permit and ask Design, Environment and Construction whether a building permit is required as well.

Homeowners can apply, with limits

Can a homeowner pull it?

The city publishes a Homeowner Permit Letter of Indemnification Affidavit for an owner who wants a homeowner permit and will serve as general contractor. The affidavit requires that the building is on property the applicant owns, will be occupied by the applicant, and will not be used by the general public; that the applicant has not sold a building they constructed and contracted within the prior 24 months; and that the property is not to be offered for sale or lease as provided in O.C.G.A. § 43-41-17. If the applicant is not installing the electrical (or plumbing or mechanical) system as the building owner, the affidavit requires them to hire properly licensed contractors and have those contractors secure the required trade permits. The Permit Requirements page also tells homeowners submitting a building permit to include the Homeowner as Contractor Affidavit, and tells trade-permit applicants to include business and state licenses. That language supports a homeowner applying for work they will actually perform, but it is not a blanket “any DIY electrical is allowed” statement. Confirm with permit staff at 404-377-6198 or permittech@decaturga.com before you do the work yourself — especially for service equipment, new circuits, or anything beyond a simple device replacement.

Official AHJ office

Office
City of Decatur Design, Environment and Construction
Division
Permitting (electrical, HVAC, and plumbing trade permits)
Address
Leveritt Public Works Building, First Floor, 2635 Talley Street, Decatur, GA 30030
Mailing
509 N. McDonough St., P.O. Box 220, Decatur, GA 30031
Phone
404-377-6198
Email
permittech@decaturga.com
Hours
Monday–Friday, 9:00 a.m.–4:00 p.m., closed 12:00 p.m.–1:00 p.m.
Portal
Community Core

Walk-in paper applications are no longer accepted. Use Community Core. Office hours below are for questions and general information.

More official contacts

Fees

The adopted FY 2025–26 Consolidated Schedule of Fees (approved June 16, 2025) lists a minimum electrical permit of $90, plus itemized charges. There is also a $25 e-permitting and digital plan review fee per item. The city calculates the total from the electrical fee table when you apply in Community Core. These figures are from the FY 2025–26 schedule; confirm they are still the current year’s rates.

ItemAmountSource note
Electrical permit, minimum $90 Listed as “Electrical permit / Minimum Permit – $90” and again on the electrical fee table.
E-permitting and digital plan review fee $25 per item Listed under Development fees in the same adopted schedule.
Residential outlets, switches, and lights $1.20 each Commercial outlets, switches, and lights are listed at $1.80 each.
Meter loops / temporary service pole examples See schedule The table lists amp-based charges for meter loops and temporary service poles (for example, 100 amps $12.00, 200 amps $19.20, 400 amps $30.00). Use the official table for the row that matches the work.
Reinspection $60 Listed under Development fees.
Starting work without a permit Double the permit fee Listed under Development fees.

The applications page says fees printed on older permit forms may be out of date and to use the current year’s fee schedule. Ask Community Core or permit staff for the exact total before you pay.

City of Decatur Consolidated Schedule of Fees, adopted FY 2025–26 (June 16, 2025)

How to apply

  1. Confirm the property is inside the City of Decatur, not unincorporated DeKalb County. They are different permit offices.
  2. If you do not already have a Community Core account, email permittech@decaturga.com with your primary contact name, email, phone, mailing address, and — if you are a contractor — state/contractor license and business license. The How to Obtain a Permit page says you will then receive a sign-in email from no-reply@communitycore.com. All applications must be submitted through www.communitycore.com; the city no longer accepts paper, email, or in-office applications.
  3. In Community Core, apply for the electrical trade permit. Homeowners should upload the Homeowner Permit Letter of Indemnification Affidavit. Contractors should upload business and state licenses, as the Permit Requirements page instructs.
  4. Pay fees in the portal. After issuance, request inspections only through Community Core.
  5. If the work also disturbs trees or critical root zones, a pre-application meeting with the city arborist is required before filing. If the property is in a local historic district, additional review applies.

Inspections

  1. All inspections must be requested through Community Core, according to the city’s How to Obtain a Permit page.
  2. Do not cover new wiring until the inspector has approved it. Ask permit staff which inspections apply to your exact scope (for example, rough-in and final for a new circuit).
  3. A certificate of completion or occupancy is requested by emailing permittech@decaturga.com only after all permitting fees are paid, all inspections have passed, any required as-built approval is done, High Performance Building Standard requirements are met, and there are no holds, stop-work orders, or citations.
  4. The adopted fee schedule lists a $60 reinspection fee.

Common pitfalls

Questions people actually ask

Does a small electrical job in Decatur still need a permit?

Yes, if you are installing, enlarging, altering, repairing, removing, converting, or replacing an electrical system. The city’s How to Obtain a Permit page says that trade-permit trigger applies regardless of value.

Can a Decatur homeowner do their own electrical work?

The city has a Homeowner Permit Letter of Indemnification Affidavit that lets an owner-occupant apply as general contractor on a home they will occupy and not offer for sale or lease, subject to O.C.G.A. § 43-41-17. If the owner is not installing the electrical system themselves, a licensed electrical contractor must get the trade permit. Confirm with city staff before you do the work yourself.

How do I apply?

Only through Community Core at www.communitycore.com. Email permittech@decaturga.com for first-time access. The city no longer accepts permit applications in the office, by email, or by mail.

What does the electrical permit cost?

The adopted FY 2025–26 fee schedule lists a $90 minimum electrical permit plus itemized charges (for example, $1.20 per residential outlet, switch, or light) and a $25 e-permitting and digital plan review fee per item. The city totals the fee in Community Core. Confirm that the FY 2025–26 schedule is still the current one when you apply.

Official sources

Every factual claim on this page is drawn from the government pages below, last checked on the date shown. If a link has moved, start at the AHJ website.

  1. City of Decatur — How to Obtain a Permit — accessed November 27, 2026; https://www.decaturga.com/dec/page/how-obtain-permit
  2. City of Decatur — Permit Requirements — accessed November 27, 2026; https://www.decaturga.com/dec/page/permit-requirements
  3. City of Decatur — Applications, Forms and Fees — accessed November 27, 2026; https://www.decaturga.com/dec/page/applications-forms-and-fees
  4. City of Decatur Consolidated Schedule of Fees, adopted FY 2025–26 (June 16, 2025) — accessed November 27, 2026; https://decaturga.civicpluswebopen.com/media/43896
  5. City of Decatur Homeowner Permit Letter of Indemnification Affidavit — accessed November 27, 2026; https://decaturga.civicpluswebopen.com/media/19706
  6. Community Core permitting portal (URL published by the city) — accessed November 27, 2026; https://www.communitycore.com

Need a licensed electrician?

Most electrical permits still end with a licensed electrician doing the work — or at least signing off on an inspection. When referral programs are activated, the buttons below will go to those partners. Until then, hire a licensed electrician who is registered with the local AHJ, and verify their license with the state licensing board.

Angi

Homeowner-to-pro quotes for electrical work, including panel upgrades, EV chargers, and generator hookups.

Referral pending

Modernize

Pay-per-lead contractor matching for home-improvement trades. Modernize also sells generator leads to contractors (install, hookup, transfer switch).

Referral pending

Local licensed contractor

A reserved slot for a direct referral agreement with a licensed electrical contractor who already works in this jurisdiction.

Ready to activate